Step #1:
Receive
PO
from Customer.
·
Verify
price per foot is correct with Quoted Price
·
Clarify all
profiles so that templates can be produced.
·
Verify when
product is to be delivered and pick-up
·
Fill out
job work scope worksheet.
Step # 2:
Process PO
into CDI work order and meet with Customer.
·
Make file
for CDI’s office that includes all detail of project as above.
·
GM or Shop
Manager will create a detailed work order to be copied 4 times.
1 for the office file , 1 for Shop
Manager or Sales Person, 1 for Finish Forman, and one for
driver.
Step #3:
Disperse work order to proper
personnel.
·
First copy
is for the office to keep on file and to use for billing
purposes. Note:
This paper work will not be placed
in the office file until the GM or Shop Manager has signed off
on the footage of material received.
Once signed of then place in office
work file.
·
Second copy
is for the shop manager records and to help set schedule and
keep record of progress.
This copy must be signed of prior
to customer pick-up.
·
Third copy
is for the Finish Forman.
This copy is to ensure the work
scope is identified for production, to clarify the lead-time and
delivery schedule, to ensure the product drop off is completed
to the customer standard, and to ensure the proper amount and
type of material is reloaded for pick-up.
Note: this paper work will only be
distributed by either the sales person, shop manager, or the GM.
·
Fourth copy
is to be given to driver to confirm receipt of order.
Also
should be signed off with copy maid for CDI’s office file.
Step # 4:
Production meeting to include the
Finish Forman, Sales Person, Shop manager, and GM if needed to
schedule material run time and tracking of project.
Production meeting to identify the following:
·
Day and
time when run will be completed.
·
Type of
material
·
Speed for
material run
·
Amount of
finish material needed and place order as needed
·
When
templates will be completed and order material as needed
·
Review work
scope worksheet and revise as needed.
·
Review
tracking form
Step
# 5:
Execute
|